Projects Of Capstone Engineering

Projects Being made By Capstone Engineering

PROJECT SUMMARY

Work Completed

–  Third floor slab form-work (laying play wood)

– Third floor beam, mo-dine and re bar work

PROJECT SUMMARY

Work Completed

July 2015

–  Second floor Column & Beam Concrete Casting Completed.

– scaffolding erecting for third floor slab.

PROJECT SUMMARY

Work Completed

July 2015

–  Third floor form work & ribbed block lying.

PROJECT SUMMARY

Work Completed

September 2015

–  Sixth floor slab , Seventh floor column & HCB Wall Block work .

Project: B+G+7 Office Building       

Client: cooperative Bank of Oromia

Location: Nekemete, Ethiopia

Contract type: Material + labor based

Project cost: 52,722,593.64

Plot area: Around 1500M2, & 7 month since the start of the project

ON Finishing

Project: Industry zone

Location: Sendafa , Ethiopia

Contract type: Material + labor

PROJECT – G+5 Apartment Building

Client : J.H.Simex Plc

Location: Addis Ababa, Ethiopia

Contract type: Material + labor based

Project cost: 82,051,642.46

Project Completed

Bole Bulubula

Addis Ababa Ethiopia

Location Addis Ababa Ethiopia

Ayat Ground +4 living apartment

Location Addis Ababa Ethiopia

Ayat Ground +2

Project Completed

Asko Site.

Location: Addis Ababa Ethiopia